工業(yè)環(huán)??照{(diào)可安裝在墻壁上,屋頂上或室外的地面上,安裝的位置最少不能低于2.25米。采用40*40*4支架與墻或窗板螺栓連接,且所有的縫隙均用玻璃膠或水泥砂漿密封。安裝風(fēng)管時(shí)要在安裝的底架上安裝吊桿,使風(fēng)管重量全部吊裝在底架上。
技術(shù)要求:
1、三角支架焊接和安裝要牢固;
2、檢修平臺(tái)必須能支撐機(jī)組和維修人員的重量;
3、主機(jī)安裝必須水平;
4、主機(jī)法蘭與送風(fēng)彎管的截面必須平齊;
5、所有外墻風(fēng)管都要做好防水處理;
6、主機(jī)接線盒必須靠室內(nèi)安裝,便于維修;
7、風(fēng)管彎頭近墻處要做防水處理,以防止水流入室內(nèi)。
evaporative air cooler can be installed on the wall, roof and outdoor ground, the installation position area is not less than 2.25 square meters.The 40*40# bracket is connected with the wall or window by the bolt,there is a rubber pad between the elbow and bracket, and all cracks are sealed with a plastic glass or cement mortar. An steeve should installed on the bottom of the bracket when we install the elbow.
Technical requirements:
1.triangle bracket welded and installed should be secured ;
2.maintenance platform must be able to support the weight of the crew and maintenance personnel;
3.the host must be installed in a horizontal positon;
4.host junction and air pipe section must be installed in horizontal position; 5.all the exterior duct must be waterproofed;
6.hostjunction box must be indoor installation;
7.duce elbow into the wall should be waterproofed in order to prevent duct flow into the Interior;
上出風(fēng)安裝示意圖
Upward-Installation method
側(cè)出風(fēng)安裝示意圖
Sideward-Installation method
下出風(fēng)安裝示意圖
Downward-Installation method